Dear partners,
The EU portal is now open for final reporting following the project end
in August. Each partner must complete their own financial report; UFR
(as coordinator) will conduct a final check but cannot enter data on
your behalf.
*Deadline:* All financial and technical reports are due within 60 days
of project end; by *29 October*. Some partners have already submitted
their financial reports; thank you. If you need any support, please let
us know.
*EGD working session (3 October, 14:00–16:00):* I will share the final
technical report as a Google Doc before the end of September. We will
use the 3rd Day of the European Galaxy Days to resolve open questions
and *nearly finish everything together*. After I shared the Google Doc,
please review the document and *come prepared with questions** and
answers*, so we can close items efficiently during the session.
*Reviewer change:* The project officer informed us that the external
reviewer will change from “Anne Koutsabeloulis” to “Veneta Panayotova
ALEKSIEVA.” Please inform us within 5 days if you have any
confidentiality objections.
Best regards,
Armin Dadras