Hi, I am currently using the reports tool to see what jobs have been executed etc ... When you look at the information for each job it states the time the job was put on the queue (creation time) not the actual start time of the job. Do you know if the start time of the job is stored somewhere? Thanks Neil
Il 2014-05-19 04:47 Neil.Burdett@csiro.au ha scritto:
Hi, I am currently using the reports tool to see what jobs have been executed etc ...
When you look at the information for each job it states the time the job was put on the queue (creation time) not the actual start time of the job. Do you know if the start time of the job is stored somewhere?
Hi Neil, take a look at this pull request, which was merged recently in galaxy-central and will be available in the next Galaxy release: https://bitbucket.org/galaxy/galaxy-central/pull-request/352/implement-plugi... Best, Nicola
participants (2)
-
Neil.Burdett@csiro.au
-
Nicola Soranzo